Gumusut-Kakap
YSSE Fabricator Engineering & Construction
Oil & gas · Piping

Gumusut-Kakap

Piping fabrication and installation, plus fibreglass gratings, for Shell's first deepwater development in Malaysia.

Client
Shell Malaysia
Location
Malaysia
Year
2012
Sector
Oil & gas
Our scope
Fabrication and installation of piping systems, and installation of fibreglass gratings
The project

Delivered on schedule with zero injuries.

Development drilling at the Gumusut-Kakap field began in January 2008. Early production started in November 2012 at around 25,000 barrels per day, with the wells tied back to the Kikeh facility operated by Murphy Sabah Oil. The semi-submersible production platform was secured on location in June 2013.

Gumusut-Kakap is Shell Malaysia's first deepwater development and a milestone for the country's offshore oil and gas industry.

YSSE fabricated and installed the piping systems and installed the fibreglass gratings. The work was completed on schedule with zero injuries recorded, drawing on years of offshore experience to meet the project's safety and quality standards.

0Injuries recorded
25,000Barrels per day at early production
Gallery11 photos · tap to enlarge
Next project Polycrystalline Silicon Plant Tokuyama Malaysia · Samalaju, Bintulu, Sarawak